Oracle finance system delays payments to Edinburgh University

November 15, 2022

Edinburgh University is still paying staff and suppliers late because of the problematic introduction of a new Oracle-based human resources and finance system.

In December 2014, the University of Edinburgh deployed the Oracle E-Business Suite (EBS) 12.1.3 for HR, payroll, and self-service. The last upgrade to this system took place in November 2013.

In June 2019, Oracle announced the university’s transition to Oracle ERP Cloud and Oracle HCM Cloud, both based on the Oracle Cloud-based fusion platform. In late summer, integration partner Inoapps announced that it had been awarded the contract to support the project. In January 2021, the first phase of the project is expected to be operational, with financial and human resources modules to follow.

Both Inoapps and Oracle declined to comment on the problematic implementation, while a university spokesman declined to deny the contents of the letter and acknowledged that problems with the new system were still ongoing.

In fact, it said “The University recently implemented a new finance system, which required us to interrupt financial processing for a period over summer to allow us to test the system and transfer huge volumes of data. This has unfortunately led to a backlog of some payments.”

The sources for this piece include an article in TheRegister.

Top Stories

Related Articles

March 3, 2026 OpenAI CEO Sam Altman admitted on Monday that the company “shouldn’t have rushed” its new agreement with more...

March 3, 2026 U.S. uninstalls of ChatGPT’s mobile app surged 295 per cent day over day on Feb. 28 after more...

March 2, 2026 Bell Canada and Telus Corp. have withdrawn competing complaints before the CRTC over fibre network access, ending more...

February 27, 2026 eBay is cutting roughly 800 jobs or about six per cent of its workforce, as the company more...

Jim Love

Jim is an author and podcast host with over 40 years in technology.

Share:
Facebook
Twitter
LinkedIn